Test Cut Checklist for a Profile CNC Demo

A machine demonstration proves that a supplier can make one good part on a good day, with their own material, their own program and their own operator. A test cut proves something narrower and far more useful: that the machine can make your part, from your extrusion, to your drawing, while you watch. The difference is preparation. Show up with a section drawing, your own profile offcuts and a gauge, and a two-hour visit produces enough evidence to write an acceptance clause. Show up empty-handed and you leave with a video and a brochure. This is the checklist we recommend buyers use before a purchase decision — and it is deliberately separate from the factory acceptance test that happens after an order is placed.

1. A demo and a FAT are not the same meeting

A demo test cut is pre-purchase: it answers whether the machine concept fits your parts, and it is where you compare two or three configurations. A factory acceptance test (FAT) is post-order: it is a contractual trial of the specific machine you bought, against pass/fail criteria written into the purchase order. Keep them separate. The demo is where you discover what those criteria should be — which feature is hard, which tolerance actually matters, how long a loaded run needs to be. Everything you learn at the demo should end up as a line in the FAT plan, not as a verbal reassurance.

2. What to send two weeks before the visit

The supplier needs time to prepare a program, tooling and fixtures. Send the section drawing of the real extrusion (including wall thicknesses and cavity positions), the feature list with hole sizes and tolerances, the alloy and temper, the surface finish if it is coated, and the length distribution of your parts. Say which features are cosmetic and which are functional. If you work in high-mix low-volume batches, send two or three different profiles rather than the easiest one — changeover behaviour is often the deciding factor, and it cannot be demonstrated on a single part.

  • Extrusion section drawing with wall thickness, cavities and datum faces marked
  • Feature list: hole diameters, slots, threads, end faces, with tolerances
  • Alloy and temper, plus any anodising or powder-coating sequence already agreed
  • Part lengths and annual or monthly mix — including the awkward ones
  • Photos of the defects you are trying to eliminate on the current process
  • The measurement method you use, and which dimensions must hold after unclamping

3. What to carry into the shop on the day

Bring your own stock. A supplier's demonstration profile is familiar to the machine, the fixture and the program; your multi-cavity extrusion with a dense hole pattern may behave quite differently. Take three or four offcuts long enough for a full clamping cycle, a printed copy of the drawing, a caliper and the gauges you would use in your own inspection, plus a marker for labelling parts. Bring the person who will program or operate the machine in production — the questions an operator asks in the first ten minutes are usually the ones that decide whether the machine gets used properly in year two.

Parallel aluminium extrusions held by blue pneumatic clamps on a machining centre table
Your own extrusion, in the supplier's clamps: section geometry and wall thickness decide fixturing before any parameter does.

4. Stand where you can see the setup, not only the screen

It is tempting to watch the control panel or the finished part. The most informative place to stand is beside the worktable, where you can see how the profile is supported, how many clamps are used, where the chips go and how the operator loads the next blank. On long extrusions, support spacing and clamp layout are often the difference between a part that holds tolerance and one that springs back when released. Ask to run a second cycle with the same setup rather than a fresh, carefully prepared one — repeatability is the point.

Worktable, clamps and tool changer of a profile CNC drilling centre seen from the operator side
Clamp positions, chip evacuation and tool access are visible from the table — and invisible from the control screen.

5. Seven things to watch while the machine runs

Observation sheet for a supervised test cut

CheckWhat to look atWhat it tells you
Clamping and supportNumber and spacing of clamps, contact with thin walls, any shimsWhether the part is being held without distortion
Chip evacuationWhere chips collect, any re-cutting, air or MQL deliveryRisk of scored surfaces and tool wear in production
Tool changesHow often, how long, whether the magazine layout suits your hole mixThe real cycle time, not the cutting time
Traverse and idle movesEmpty travel across a long profile between featuresWhy hole pattern can matter more than hole count
BreakthroughExit burrs, chatter at thin cavity walls, noise under loadFixture rigidity and tool condition
Program editHow a dimension or hole position is changed on the controlWhether your own team can run high-mix work without a programmer
Repeat cycleSecond and third part, same setup, measured the same wayConsistency, which a single perfect sample cannot prove

6. Measure after unclamping, not while the part is on the table

A part clamped flat can measure perfectly and still move when released, especially a thin-walled or asymmetric extrusion. Agree the measurement stage before the first cut: take the part off the machine, let it reach shop temperature, then measure hole position and any flatness or straightness callouts on a surface plate with the gauges you brought. Label the first, second and third parts and keep them. Photograph the setup next to the part. These three samples and the notes are the evidence base for the acceptance criteria you will later write into the order.

Visitors seen from behind watching a profile machining centre demonstration with the guard open
A supervised test cut, viewed from behind: the buyer, the operator and the same part on the table.

7. Red flags worth acting on

A good supplier is not one that hides nothing going wrong — on a real test cut something usually needs adjusting. The signal is how it is handled. Be cautious if the demo uses only the supplier's own sample profile after you sent your own drawing, if the loaded run lasts only a few minutes, if measurement is done before unclamping, if a program change requires a remote engineer, or if the quote afterwards contains none of the details you agreed on the shop floor. Each of these is cheap to resolve before an order and expensive afterwards.

  • Your drawing was supplied, but the cut ran on stock demonstration material
  • Only one part was produced, or parts two and three were not measured
  • Dimensions were checked while the profile was still clamped
  • Tooling, clamp layout or program changes cannot be shown on the control
  • No written record of the agreed test piece, tolerance or measurement method

8. Turn the demo notes into the purchase order

Within a day of the visit, write down the model and configuration, the test piece (your profile, by drawing number), the features cut, the measurement method and results for all three parts, the clamp and tooling layout, the cycle time observed, and the program-editing demonstration. Attach the photographs. These points become the acceptance criteria in the FAT clause, the training scope in the installation plan and the spare-tool list in the quotation. This is also the moment to ask which configuration actually fits the mix: OMEX builds profile drilling and milling centres across short, medium and long-stroke formats, and a demo on your own parts is the cheapest way to find out whether you need a larger table or simply a better fixture.

Frequently asked questions

Should I bring my own material to a CNC machine demonstration?
Yes, whenever possible. A demonstration profile is optimised for the machine and the program. Your own extrusion — with its wall thickness, cavities and surface finish — is what reveals clamping, chip evacuation and breakthrough behaviour. Send the drawing beforehand so the supplier can prepare tooling.
What is the difference between a demo test cut and a FAT?
A demo test cut happens before purchase and helps you choose the configuration and define realistic acceptance criteria. A FAT happens after the order, on the actual machine being shipped, against pass/fail criteria written into the contract. The demo should feed the FAT plan.
How many parts should a test cut produce?
At least three from the same setup, measured the same way. One part proves capability; three show consistency and expose thermal drift, tool wear and clamping variation. For a long profile, ask for a continuous run long enough to see the machine after it has warmed up.
Who should attend the demonstration?
The person who will program or operate the machine, plus whoever signs off on quality. An operator will ask about setup, program editing and chip clearing — the questions that determine day-to-day productivity — while a quality engineer will settle the measurement method.
Can I keep the sample parts, the program and the measurement record?
Ask for all three in advance. The labelled samples and the measurement sheet are the baseline for later acceptance, and the program (or a screen capture of the setup) tells your team how much work is really involved in a changeover. Agree any confidentiality limits before the visit.
What should appear in the quotation after the demo?
The exact configuration, clamp and tooling layout, the test-piece drawing number, the measured results, the agreed tolerance and measurement method, the cycle time observed, and the training and installation scope. If the quote does not reflect what was demonstrated, the demo has not been carried into the contract.

Back to all articles

Need an assessment for your application?

Tell us the workpiece material, length and required operations, and we will evaluate the machine and fixturing solution.

Get a Quote